Do I Need Planning Permission for a Fence?

Written by James Walker · Last reviewed 15 August 2026

James Walker has 2 degrees in construction (BSc (Hons) Building Surveying · MSc Environmental Design of Buildings) and an extensive background in issue resolution, resolving over £4 billion of consumer issues.

The short answer

  • 2 metres maximum without permission, measured from ground level.
  • 1 metre where the fence is next to a highway used by vehicles, or its footpath.
  • The height includes any trellis or topper. A 1.8m fence with a 30cm trellis is a 2.1m fence.
  • On a corner plot, the side boundary along the road is in the 1-metre zone too.
  • Listed buildings, conservation areas and Article 4 directions all change this.
On this page

Applies to England and Wales.

The limits

A gate, fence, wall or other means of enclosure is permitted development if it does not exceed:

  • 1 metre above ground level where it is next to a highway used by vehicular traffic, or the footpath of one
  • 2 metres above ground level anywhere else

Schools have a specific allowance, and can go to 2 metres next to a highway provided anything above 1 metre does not obstruct the view of highway users dangerously.

The trellis trap

The height limit is inclusive of everything on top. Trellis, lattice, finials, all of it counts, and measurement is from the highest point.

This is the most common way a perfectly ordinary fence ends up needing permission that nobody applied for.

Corner plots and "adjacent"

On a corner plot, the side boundary running along the road is subject to the 1-metre limit, not the 2-metre one. People routinely discover this after building.

"Adjacent to a highway" is not precisely defined in the legislation, and local authorities interpret it differently, some treat a metre or two as the threshold, others more. Where a boundary is anywhere near a road, ask the council rather than assuming.

Replacing an existing fence

If a fence already exceeds the limits, you can maintain, improve or replace it, provided the height is not increased. A 2.5-metre fence can be replaced with another 2.5-metre fence.

This does not apply in a conservation area or in the grounds of a listed building.

Before you build

Establish whose boundary it is. This causes more trouble than the planning rules do. Check the title deeds. If ownership is unclear, speak to the neighbour before starting, not after, a fence on a disputed line may have to come down.

How it works

Help your project succeed with Trusted Payments

Trusted Payments project flow: create a project, add a completion payment, manage the project in the app, pay by milestones, snagging and handover, 24-month warranty, and independent resolution if needed.
See how it works

Related guides

Common questions

Do I need permission to remove a fence?
Not usually on your own land, but you may in a conservation area.
Can my neighbour make me lower my fence?
Not if it is within limits and on your land. Above them, the council can act.
What about hedges?
Not planning-controlled, but high hedges have their own complaints procedure.
Does a trellis really count?
Yes. Every time.